Compulsory Alternative Dispute Resolution
Contents |
[edit] Introduction
Construction contracts usually provide for disputes to be dealt with by agreed dispute resolution procedures involving mediation, adjudication and arbitration. Often a combination of all three.
A very wide range of Alternative Dispute Resolution techniques are available. For more information, see Alternative dispute resolution.
[edit] Compulsory ADR report
In July 2021, the ‘Civil Justice Council Compulsory ADR report’ was published. The document was produced after Sir Geoffrey Vos, the Master of the Rolls asked the Civil Justice Council to review the legality and desirability of compulsory ADR. The conclusion of the report upheld the legality of compulsory ADR under Article 6 of the European Human Rights Convention.
Chair of the Judicial/ADR Liaison Committee and lead Judge for ADR Lady Justice Asplin acknowledged that more work needed to be done on the subject, but she concluded that ADR can - and should - be made compulsory under certain situations. She sees this as a necessary step in changing the overall cultural attitude towards ADR, which she feels will be beneficial for all parties involved.
Vos said the report will reshape the ADR process by stressing resolution rather than dispute. He said, “ADR should no longer be viewed as ‘alternative’ but as an integral part of the dispute resolution process.”
The report represented a change from the judicial approach of Lord Justice Dyson in 2011 who expressed concerns not only about the legality of compulsory ADR, but of its desirability.
Some experts see the shift as a reaction to UK courts that have become overwhelmed by an increasingly unmanageable backlog of cases. Under the revised approach, courts may begin to order parties to engage in ADR processes, especially if judges feel this will expedite an affordable resolution.
[edit] Call for Evidence
On 3 August 2021, the Ministry of Justice responded to the findings of the Civil Justice Council’s report on compulsory alternative dispute resolution by opening an eight week call for evidence on Dispute Resolution in England and Wales. The primary purpose of the measure is to seek input on the best ways to settle disputes.
The Ministry of Justice hopes to revise the system in a manner that decreases the number of cases that unnecessarily rely on the courts for resolution. Instead, it hopes to increase the uptake of less adversarial options through the introduction of innovative, technologically advanced processes. One approach under consideration is the promotion of pre-claim portals and court processes with integrated mediated resolution interventions.
[edit] Related articles on Designing Buildings
- Alternative dispute resolution.
- Alternative Dispute Resolution legislation.
- Causes of construction disputes.
- Conflict avoidance.
- Dispute avoidance.
- Dispute resolution.
- Dispute resolution procedure.
- Litigation.
- Mediation.
[edit] External resources
- Courts and Tribunals Judiciary, Civil Justice Council Compulsory ADR report.
- Ministry of Justice, Dispute Resolution in England and Wales.
Featured articles and news
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.